another busy day firstly we had to complete the previous task of installing the spotlights at Guest house gardens and it was done....second task for the day was to wire and install temporary infra red lights at Wild Life Centre.
the lights will be pluged in to be switched when needed.
we used 1,5mm surfix cable,Edison screw bulb holders and three pin plugs.
we completed our day with installaton of plugs at the mechanical workshop were two plugs had to share a circuit and one on its own circuit.
The installation was done accordingly but we encounted a problem were one circuit was tripping the Earth Leakage.
The problem was later discovered that the neutral on one circuit was connected on the neutral bar of the supply which is earth potential.